=(37.8+11.22)×0.18×0.24=2.12 m
3
钢筋工程量:
∮12:L =(圈梁长度+T形接头锚固长度×T形接头个数)×主筋根数
=[37.8+11.22+(30d+6.25d)×4]×4=(49.02+1.74)×4
=203.4m
∮6.5:L=(圈梁长/箍筋间距+墙根数)×每根箍筋长
=(37.8+11.22/0.2+6)×[2×(0.21+0.15)+12.5×0.0065]
=203.1m
地圈梁钢筋用量:
∮12:203.04×0.888=180.30kg
∮6.5:201.10×0.260=52.29km
4.独立柱基:
混凝土工程量扩大面以下六面体体积+扩大面以上四棱台体积
=2.1 × 2.1×0.3+0.4/6×[2.1×2.1+0.5×0.5+(2.1+0.5)2]
=1.323+0.761 3-2.084m
3
钢筋工程量:∮10:L=(2.1-0.07+12.5d)×(2.1/0.15+1)×2=64.65m
独立柱基础钢筋:∮10:64.65×0.617=39.889kg
5.无筋混凝土垫层=2.3× 2.3×0.1=0.529m
3
6.条形砖基础:基础长度计算:
L1-1=8.1×2+*3.6-0.24)=19.56m
L2-2=10.8×2+(8.1-0.24)=29.46m
V砖基=(基础深+大放脚折高度)×基础宽×基础长嵌入基础的构件体积
=(1.4+0.394)×0.24×19.56+(1.4+0.656)×0.24×29.46-地圈梁
=8.421+14.536-2.12
=20.84m3
7.砖基混凝土垫层=1.2×0.45×[(8.1×2+3.6-1.2)+(10.8×2+8.1-1.2)]=25.43m
3
8.基础回填土=挖土体积-室外地坪标高以下埋设物的体积
式中:
埋设物体积中应加上室外地坪标高以下柱体积=0.4× 0.4×(1.05-0.15)=0.144m
3
砖基础体积中应扣除室内外高差部分体积=0.15×0.24×(19.56+29.45)=1.764m
3
V基填=挖基础土方-(地圈梁+柱基+柱基垫层+砖基础+砖基垫层+柱体积)
=98.92-[(2.12+2.084+0.529+(20.84-1.764)+25.43+0.144)]
=98.92-49.38
=49.54m3
9.室内回填土=底层主墙间净面积×(室内外高差-地坪厚度)
=[11.04×8.34-(19.56+29.45)×0.24]×(0.15-0.08)
=(92.07-11.765)×0.07
=5.62m
3
10.土方场内场内运输=挖土总体积-填土总体积
=98.92-(49.54+5.62)=43.76m
3
计算结果列入工程量汇总表,见表 3-1
序号 |
分项工程名称 |
计量单位 |
工程量 |
序号 |
分项工程名称 |
计量单位 |
工程量 |
1 |
人工挖土方2米以内三类 |
m3 |
98.92 |
8 |
现浇地圈梁混凝土 |
m3 |
2.12 |
2 |
基础回填土夯实 |
m3 |
49.54 |
9 |
现浇构件钢筋:∮12 ∮10 |
T |
0.1803 |
3 |
室内回填土夯实 |
m3 |
5.62 |
0.040 |
4 |
平整场地 |
m2 |
92.07 |
0.0523 |
5 |
人工运土方200米以内 |
m3 |
43.76 |
10 |
砖基混凝土垫层 |
m3 |
25.43 |
6 |
砖基础 |
m3 |
20.84 |
11 |
柱基混凝土垫层 |
m3 |
0.529 |
7 |
现浇独立柱混凝土 |
m3 |
2.084 |
|
|
|
|